ENGINEERING NOTE · OBSOLESCENCE & LAST-TIME-BUY

Component lifecycle, not capacity, breaks the programme

Semiconductor average life has fallen from about 30 years to about 10, while the equipment those boards sit in is expected to run for 20–30. Capacity problems can be scheduled around; a last-time-buy notice cannot. This note sets out the scan items, the J-STD-048 notice clock, the last-time-buy quantity rule and the substitution rule.

The process engineering team · 11 September 2026

WHY PROGRAMMES BREAK

Four numbers that move a delivery schedule

Capacity is a scheduling problem: add a shift, move a build date, quote a longer lead time. A component that reaches end-of-life is a design problem, and it arrives with a document rather than a delay note.

  • ~30 → ~10 years Average semiconductor lifespan
  • ~750,000 Components obsoleted, 2022
  • 470,000 Reached end-of-life, 2023
  • 26–40+ weeks DRAM lead times

Industry-published figures, used here as illustration, not as our own measurements.

WHAT A BOM RISK SCAN ACTUALLY CHECKS

The checks, in order

The scan runs on the bill of materials as received, line by line, before a quotation is treated as firm. Each check exists because it changes what can be promised about the build date.

BOM risk scan items and the action each one triggers
Check What we look at What it triggers
Lifecycle statusActive / NRND / EOL Every MPN against its manufacturer status, plus the published last-order date where one exists NRND and EOL lines are listed for the customer with a recommended action and the date the decision has to be made by
Single sourceno second source Any MPN with one manufacturer, one package option and no drop-in alternative on the approved vendor list Flagged for a second-source qualification before the next build, with the parameter comparison done first
Long leadagainst the build date Quoted lead time measured back from the required ship date, including the 12–26 weeks a long-lead semiconductor can add Either the build date is re-planned, or the part is bought ahead and held against the programme
Counterfeit riskAS5553 / AS6081 Source of supply and lot traceability, checked against the AS5553 and AS6081 anti-counterfeit practices Franchised or authorised supply only for the affected lines, with incoming inspection on those lots
ComplianceRoHS / REACH / 3TG RoHS and REACH SVHC status of the MPN, and the conflict-minerals position reported through the CMRT Declarations requested from the manufacturer, or the part is replaced before the design is frozen

Declarations and test reports are available on request, and the CMRT is refreshed annually.

THE NOTICE CLOCK

Twelve months, then six

When a manufacturer discontinues a part, the useful information is not the announcement but the two dates attached to it. Those dates are what a programme manager can put into a schedule, and they come from J-STD-048.

J-STD-048 · last order date
12 months
J-STD-048 · final delivery
6 months after
J-STD-046 · change notification
process and material changes
Industry-published DRAM lead time
26–40+ weeks

Twelve months sounds generous until it is laid against a validation cycle. A medical or automotive build has to re-qualify the assembly, and a first-article approval on a new part can consume a large part of that window before a purchase order is even placed.

Notification is not guaranteed. Parts are discontinued without a buy window, distributors hold stock that is not covered by the manufacturer's notice, and a part that has already passed its last-order date is only available from the open market — which is where the counterfeit risk in the fourth scan line becomes a live problem rather than a checkbox.

PLANNING A LAST-TIME-BUY

Quantity, storage, and what you must not guess

The quantity is arithmetic, not optimism. It is built from what the programme still has to produce, and it is agreed with the customer before the order is placed, because it is the customer's forecast that sets the number.

Remaining production years × annual usage
base quantity
Attrition for scrap and rework
added
Samples for verification and first article
added
Reserve for a later process change
agreed, not assumed

STORING WHAT YOU BOUGHT

Parts that sit for years still have to solder

Buying the last reel only moves the problem if the reel is stored badly. Moisture and oxidation decide whether the parts are still usable when the programme reaches them.

Packaging
MBB + desiccant + humidity indicator card
MSL floor life
per level, logged on opening
Exposure beyond the limit
bake before use
After long storage
solderability and appearance re-verification
Records
lot-level traceability

A grid-equipment manufacturer in the Netherlands moved a 2-layer power board to a BOM risk scan, a second-source qualification and a last-time-buy plan; the product's production life was extended by five years.

SECOND SOURCES NEED WRITTEN APPROVAL

No automatic substitutions — ever

Replacing a part is a design change, and it is treated as one even when two parts look identical on paper. The six steps below are the route a substitution takes, and the third one is not optional.

Scan flag

The scan raises the MPN with its status and the reason: NRND, EOL, single source, long lead or a compliance gap. The reason decides how much time the programme actually has.

Parameter comparison

An engineer compares the parameters that matter to the circuit — ratings, package and land pattern, temperature range, tolerance and derating — against candidates, starting inside the approved vendor list.

Written customer approval

Every substitution requires written customer approval. No automatic substitutions.

Samples and verification

Samples are built and verified against the customer's test specification, with a first-article inspection report on the new part before any volume build is released.

Documentation

The comparison, the FAI report and the customer's written release go into the build file, so the next order and the next audit start from the same record.

AVL and change notice

The part is added to the approved vendor list and the change is notified under the project's change process, with the effective date and the serial range it applies from.

Softly lit out-of-focus circuit board surface with faint copper traces and via pads